The Fort Worth Press - Colosseum Bankable Feasibility Study Advances to Final Stages

USD -
AED 3.672497
AFN 64.999819
ALL 81.216919
AMD 362.051328
ANG 1.789785
AOA 917.00025
ARS 1515.25437
AUD 1.437426
AWG 1.80125
AZN 1.697326
BAM 1.739803
BBD 2.01708
BDT 123.195303
BGN 1.747831
BHD 0.378775
BIF 2997.464751
BMD 1
BND 1.281146
BOB 11.69239
BRL 5.065101
BSD 1.001468
BTN 95.050483
BWP 13.720589
BYN 3.015879
BYR 19600
BZD 2.014233
CAD 1.414935
CDF 2313.499181
CHF 0.825932
CLF 0.024881
CLP 979.255437
CNY 6.691203
CNH 6.685309
COP 3173.953654
CRC 455.099408
CUC 1
CUP 24.035938
CVE 98.087444
CZK 21.685496
DJF 178.33919
DKK 6.651198
DOP 61.433083
DZD 133.824668
EGP 53.529689
ERN 15
ETB 163.585998
EUR 0.889897
FJD 2.26765
FKP 0.750253
GBP 0.752078
GEL 2.590432
GGP 0.750253
GHS 11.695058
GIP 0.750253
GMD 73.49623
GNF 8810.21216
GTQ 7.652004
GYD 209.527198
HKD 7.84815
HNL 26.885202
HRK 6.703803
HTG 131.147978
HUF 323.552009
IDR 18053
ILS 3.09465
IMP 0.750253
INR 94.965504
IQD 1518.213762
IRR 1795877.497557
ISK 121.179576
JEP 0.750253
JMD 159.195837
JOD 0.709012
JPY 158.015022
KES 130.098296
KGS 87.449938
KHR 4070.631144
KMF 439.999825
KPW 899.999961
KRW 1334.740045
KWD 0.31082
KYD 0.834586
KZT 453.195748
LAK 22534.359294
LBP 89683.40524
LKR 331.690611
LRD 170.751234
LSL 16.462394
LTL 2.95274
LVL 0.60489
LYD 6.431526
MAD 9.729662
MDL 17.966464
MGA 4507.405595
MKD 54.836988
MMK 2100.071343
MNT 3596.488264
MOP 8.096339
MRU 40.037362
MUR 47.229488
MVR 15.459712
MWK 1736.600987
MXN 18.472997
MYR 4.083203
MZN 63.902819
NAD 16.462394
NGN 1331.2103
NIO 36.854512
NOK 9.427699
NPR 152.081128
NZD 1.770298
OMR 0.382413
PAB 1.001468
PEN 3.444825
PGK 4.547436
PHP 62.985976
PKR 277.237468
PLN 3.894835
PYG 5719.877241
QAR 3.660721
RON 4.7306
RSD 104.461148
RUB 84.13468
RWF 1478.183516
SAR 3.752837
SBD 8.064647
SCR 13.905529
SDG 601.496371
SEK 9.912398
SGD 1.282096
SHP 0.754745
SLE 24.680036
SLL 20969.504398
SOS 572.343548
SRD 37.794503
STD 20697.981008
STN 21.794245
SVC 8.763065
SYP 13001.999685
SZL 16.455989
THB 33.444972
TJS 9.228751
TMT 3.51
TND 2.98768
TOP 2.40776
TRY 49.513801
TTD 6.798915
TWD 32.453598
TZS 2646.44398
UAH 44.920874
UGX 4136.458658
UYU 40.314905
UZS 12073.121914
VES 878.910597
VND 25894.5
VUV 119.385856
WST 2.787824
XAF 583.73441
XAG 0.017551
XAU 0.000240063761
XCD 2.70255
XCG 1.804919
XDR 0.707052
XOF 583.73441
XPF 106.089045
YER 236.150057
ZAR 16.50875
ZMK 9001.193843
ZMW 20.049815
ZWL 321.999592
SSP 5750.775019
MXV 2.085785
  • RIO

    -0.3300

    97.04

    -0.34%

  • CMSC

    -0.0400

    20.67

    -0.19%

  • RELX

    0.0000

    33.41

    0%

  • RBGPF

    0.0000

    67.95

    0%

  • BCE

    -0.0700

    21.99

    -0.32%

  • BCC

    -0.0300

    75.66

    -0.04%

  • GSK

    0.8600

    51.08

    +1.68%

  • JRI

    -0.0300

    11.52

    -0.26%

  • NGG

    -0.1200

    76.68

    -0.16%

  • CMSD

    0.0900

    20.54

    +0.44%

  • BTI

    -0.0800

    55.75

    -0.14%

  • AZN

    2.0200

    168.1

    +1.2%

  • BP

    -1.4200

    43.16

    -3.29%

  • RYCEF

    0.4600

    19.7

    +2.34%

  • VOD

    0.0700

    17.02

    +0.41%

Colosseum Bankable Feasibility Study Advances to Final Stages
Colosseum Bankable Feasibility Study Advances to Final Stages

Colosseum Bankable Feasibility Study Advances to Final Stages

SAN BERNARDINO, CALIFORNIA / ACCESS Newswire / January 20, 2026 / Dateline Resources Limited (ASX:DTR)(OTCQB:DTREF)(FSE:YE1) (Dateline or the Company) is pleased to provide an update for the Colosseum Project Bankable Feasibility Study (BFS) that is currently underway.

Text size:

Highlights

  • Key major work programs completed or well advanced: Strongly confirms the parameters and assumptions from the Scoping Study.

  • Metallurgical test-work confirms 91-92% Gold recovery: Leach test-work has confirmed a recovery of 91-92% at a 106µm grind size, in line with the previous mining parameters.

  • Positive geotechnical results: Test-work supports the potential for more efficient open pit design compared to earlier estimates.

  • Mine design and scheduling underway: Whittle pit optimizations underway using operating cost inputs based on received quotes and technical inputs.

  • Historical concrete pad structures uncovered: Excavation has confirmed the presence of key processing plant foundations, which may be reused and deliver schedule and cost savings.

  • Closed loop water management system: As a result of moving to an environmentally responsible closed loop water management system for Colosseum, Dateline is planning on incorporating a filter plant to produce a stable dry stacked tailings impoundment, rather than a traditional tailings dam facility.

  • Long lead items negotiations underway: Key items to be ordered prior to the completion of the BFS. Negotiations are advanced on several of these items.

  • Strong gold price to have material impact on economics: Since the Updated Scoping Study was released in May 2025 using a gold price assumption of US$2,900/oz, the price has increased materially to over US$4,600/oz. This change is expected to have a strong positive impact on the Colosseum economics.

Dateline's Managing Director, Stephen Baghdadi, said:

"The Colosseum project is progressing to plan, with all key workstreams advancing in parallel. It's business as usual; our focus remains firmly on delivering the final stages of the Bankable Feasibility Study and the construction tasks ahead. The alignment of current results with historic mine performance confirms that Colosseum is a well-understood system, positioning the project for a lower-risk and efficient redevelopment."

Significant progress has been made on the BFS, with most of the key inputs or assumptions used in the Scoping Study confirmed in the recent test-work programs. The study reflects updated capital inputs, including several additional components, which remain modest and are more than offset by the improved revenue outlook driven by increased gold prices.

Positive Metallurgical Test-work

The metallurgical test-work program was designed to test the assumption that the actual 1990's mine production recovery was suitable to be used going forward for the new mine development.

McCarl's Tech Services, a respected metallurgical laboratory in Denver, Colorado, completed assessment of the leach dynamics at a range of different grind sizes on representative samples from the Colosseum deposit.

In line with expectations, the test-work demonstrated that at a grind size of 106µm (the same as the historical mine operation) a recovery rate of 91-92% was achieved, as was used in the Scoping Study assumption of 92%, which was initially derived from processing operations in the original mining campaign between 1986 and 1992. The result confirms assumptions made throughout the BFS and adds confidence to a conventional standard Carbon-in-Leach (CIL) processing route that was selected at the commencement of the BFS.

Positive Geotechnical Results

Agapito Associates (Agapito) was contracted to assess the geotechnical aspects of both the Colosseum mine as well as the waste rock disposal and tailings disposal for Colosseum. Test-work completed by Agapito included extensive mapping of the existing pit walls, geotechnical logging of orientated core, rock strength testing and frictional angle test work.

The now completed test-work focused on understanding the geology, rock competency, and structural architecture of the deposit to optimize pit wall stability and confirm mining angles that support long-term, safe, and efficient operations.

The test-work results support the potential for an improved open pit design relative to earlier assumptions, including the opportunity for a reduced strip ratio and associated economic benefits. The geotechnical results will be used by the mining engineers in the mine design and scheduling work.

Mine Design and Scheduling Underway

Dateline undertook a large program of drilling in the second half of 2025 aimed at upgrading Inferred mineral resources to Indicated as well as better defining the edges of the deposit.

The information gained from this drilling has been modelled and is now being used to design the South and North open pits at Colosseum. It is expected that, as with the Scoping Study, a set of staged pits will be developed to maximize value from the deposit.

The cost and design inputs for the mine design have been derived from quotes received and updated technical inputs, as highlighted through this announcement. The updated design and schedule are expected to be finalized in the near term and then incorporated into the financial modelling for Colosseum.

Historic Pads Uncovered

Mining at Colosseum was suspended in the early 1990s, after which the historic processing plant pad was covered and preserved beneath overlying material. A Lidar survey completed by Dateline in 2025 successfully delineated the location of this historic plant footprint and excavation confirmed the presence of intact concrete foundations.

Subsequent excavation has now exposed substantial elements of the former processing infrastructure, including leach tank footings, mill foundations, crusher tunnel and associated concrete pads.

The Company's engineering team is currently assessing the suitability of these foundations for incorporation into the planned redevelopment, presenting a potential opportunity to reduce both construction timelines and capital requirements as the project advances.

Figure 1: Uncovered concrete structures at Colosseum
Figures 2: Uncovered concrete structures at Colosseum

Closed Loop Water Management System

The historic Colosseum operation utilized a conventional wet tailings dam, consistent with industry practice at that time, whereby fine tailings produced during the gold leaching process were deposited in a tailings storage facility.

For the planned redevelopment of Colosseum, Dateline will use a dry-stack tailings process through the incorporation of a filter press within the processing circuit. This process mechanically removes moisture from the tailings prior to discharge, enabling materially higher levels of water recycling and the production of relatively dry tailings.

Process engineers are finalizing the assessment of belt and plate filter technologies for installation at Colosseum, with the belt filter configuration currently emerging as the preferred option. The filter plant has been identified as a long-lead item and will be prioritized for early procurement to support the Project's development schedule.

Figure 3: Closed loop water management system that recycles the water used in processing and the captured rainwater.
Figure 4: Long term planning for post completion of mining Plan

Long Lead Items

As the Bankable Feasibility Study progresses toward completion, the BFS team has proactively identified several long-lead capital items that are critical to the project's construction schedule, including the ball mill, SAG mill, filter plant, electrical transformer and other process items. Early identification of these items enables the Company to optimize procurement strategies and maintain schedule certainty.

In response, the Company and its engineering team are advancing a staged procurement plan, including placing advance orders for new equipment and assessing suitable second-hand alternatives available on shorter delivery timelines. It is anticipated that orders and/or binding options over key equipment will be secured ahead of BFS completion to support an efficient and timely mine development.

Positive Gold Price Increase

The original Scoping Study completed in October 2024 was based on a gold price assumption of US$2,200/oz, at a time when the prevailing spot price was approximately US$2,730/oz. On that conservative pricing basis, the study outlined a development scenario incorporating the recovery of approximately 635,000 ounces of gold.

In May 2025, the Company released an updated Scoping Study applying a revised gold price assumption of US$2,900/oz, while retaining all other technical, operating, and modelling assumptions from the original study. This update was intended to illustrate the sensitivity of the project to changes in the gold price environment rather than represent a revised mine plan.

Since that time, the gold price has continued to strengthen, currently exceeding US$4,600/oz. The sustained strength in the gold price is anticipated to support a stronger revenue profile as mine design and scheduling work is finalized.

The full implications of current gold price levels will be assessed as part of the ongoing Bankable Feasibility Study, which will incorporate detailed engineering, scheduling, and cost estimates to provide a comprehensive and current assessment of project economics.

Upcoming BFS Work Programs

Following the recent agreement relating to the nearby water bores, a drilling contractor has mobilized to site to undertake bore clean-out activities and flow testing. This program is expected to be completed over the next two to four weeks.

As noted, the mine design and scheduling work stream is currently underway, as is progression of the filter plant studies. A plan for civil pre-works is being developed to ensure timely construction of the mine.

This press release has been authorized for release by the Board of Dateline Resources Limited.

For more information, please contact:

Stephen Baghdadi
Managing Director
+61 2 9375 2353

Andrew Rowell
Corporate & Investor Relations Manager
+61 400 466 226
[email protected]
www.datelineresources.com.au

Follow Dateline on socials:
X - @Dateline_DTR
Truth Social - @dateline_resources
LinkedIn - dateline-resources
YouTube - @dateline.resources

About Dateline Resources Limited

Dateline Resources Limited (ASX:DTR)(OTCQB:DTREF)(FSE:YE1.F) is an Australian company focused on mining and exploration in North America. The Company owns 100% of the Colosseum Gold-REE Project in California.

The Colosseum Gold Mine is located in the Walker Lane Trend in East San Bernardino County, California. On 6 June 2024, the Company announced to the ASX that the Colosseum Gold mine has a JORC-2012 compliant Mineral Resource estimate of 27.1Mt @ 1.26g/t Au for 1.1Moz. Of the total Mineral Resource, 455koz @ 1.47/t Au (41%) are classified as Measured, 281koz @1.21g/t Au (26%) as Indicated and 364koz @ 1.10g/t Au (33%) as Inferred.

On 23 May 2025, Dateline announced that updated economics for the Colosseum Gold Project generated an NPV6.5 of US$550 million and an IRR of 61% using a gold price of US$2,900/oz.

The Colosseum is located less than 10km north of the Mountain Pass Rare Earth mine. Planning has commenced on drill testing the REE potential at Colosseum.

Dateline has also acquired the high-grade Argos Strontium Project, also located in San Bernadino County, California. Argos is reportedly the largest strontium deposit in the U.S. with previous celestite production grading 95%+ SrSO4.

Forward-Looking Statements

This announcement may contain "forward-looking statements" concerning Dateline Resources that are subject to risks and uncertainties. Generally, the words "will", "may", "should", "continue", "believes", "expects", "intends", "anticipates" or similar expressions identify forward-looking statements. These forward-looking statements involve risks and uncertainties that could cause actual results to differ materially from those expressed in the forward-looking statements. Many of these risks and uncertainties relate to factors that are beyond Dateline Resources' ability to control or estimate precisely, such as future market conditions, changes in regulatory environment and the behavior of other market participants. Dateline Resources cannot give any assurance that such forward-looking statements will prove to have been correct. The reader is cautioned not to place undue reliance on these forward-looking statements. Dateline Resources assumes no obligation and does not undertake any obligation to update or revise publicly any of the forward-looking statements set out herein, whether as a result of new information, future events or otherwise, except to the extent legally required.

Competent Person Statement

Sample preparation and any exploration information in this announcement is based upon work reviewed by Mr Greg Hall who is a Chartered Professional of the Australasian Institute of Mining and Metallurgy (CP-IMM). Mr Hall has sufficient experience that is relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting Exploration Results, Mineral Resources and Ore Reserves" (JORC Code). Mr Hall is a Non-Executive Director of Dateline Resources Limited and consents to the inclusion in the report of the matters based on this information in the form and context in which it appears.

Company Confirmations

The Company confirms it is not aware of any new information or data that materially affects the information included in the announcements dated 23 October 2024 with regard to the Colosseum MRE and 23 May 2025 with regard to Colosseum Project Economics. Similarly, the Company confirms that all material assumptions and technical parameters underpinning the estimates and the forecast financial information referred to in those previous announcements continue to apply and have not materially changed.

SOURCE: Dateline Resources Limited



View the original press release on ACCESS Newswire

K.Ibarra--TFWP